The short answer

What should an Electrical Installation Certificate include?

An EIC based on the BS 7671 Appendix 6 model has ten parts: client (A), installation and extent of work (B), design, construction and inspection signatures with any departures (C), the next inspection interval (D), signatory details (E), supply characteristics and earthing (F), installation particulars (G), the schedule of inspections (H), comments on the existing installation (I) and the attached schedules (J). It is only valid with the schedules of inspection, circuit details and test results attached.

2,600+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5

Key takeaways

  1. 01Regulation 644.1 requires an EIC for a new installation, an addition or alteration, and any replacement of a consumer unit or distribution board.
  2. 02Regulation 644.3 makes the schedule of inspections, the schedule of circuit details and the schedule of test results part of the certificate. Without them it is not valid.
  3. 03Regulation 644.4 requires the recommended interval to the first periodic inspection to be recorded. On the model form that is Section D.
  4. 04Departures are recorded in Section C against Regulations 120.3, 133.1.2, 133.1.3 and 133.5. A permitted exception to RCD protection of sockets (Regulation 411.3.3) needs its risk assessment attached.
  5. 05The prospective fault current entered in Section F is the greater of the prospective short-circuit current and the prospective earth fault current.
  6. 06An EIC is never used for periodic inspection. An existing installation gets an Electrical Installation Condition Report.

01 · Certificate Guide

When the EIC is the right certificate

Regulation 644.1 requires an Electrical Installation Certificate on completion of a new installation, or an addition or alteration to an existing one, including the replacement of a distribution board or consumer unit. It is issued to the person who ordered the work.

  • New installation, new circuit, or consumer unit or distribution board change: EIC.
  • Addition or alteration that does not add a circuit or change a board: a Minor Electrical Installation Works Certificate is allowed instead, one per circuit (Regulation 644.4.201). The model notes also allow a single EIC in place of several minor works certificates.
  • Inspection of an existing installation: an Electrical Installation Condition Report, never an EIC.

For the borderline cases, see when an EIC is required and EICR vs EIC.

Free download · PDF

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Certificate Guide

Sections A and B: client, address and extent

Section A is the client. Section B is the installation address, a description of the installation, and the extent covered by this certificate, ticked as a new installation, an addition, or an alteration to an existing installation.

Write the extent precisely

The extent defines what you are certifying. "Consumer unit replaced, circuits 1 to 9 reconnected and tested" is defensible; "electrical work" is not. Anything outside the extent stays outside your certificate.

03 · Certificate Guide

Section C: design, construction and inspection signatures

Section C has three declarations: for design, for construction, and for inspection and testing. One person can sign all three on a single-signature form where they did all three. Regulation 644.5 requires the certificate to be signed or authenticated by skilled persons competent to verify that BS 7671 has been met.

  • Each declaration states compliance with BS 7671:2018 as amended to a date: write the amendment date in full.
  • Each has its own box for departures from BS 7671, referenced to Regulations 120.3, 133.1.2, 133.1.3 and 133.5. A departure is a deliberate choice by the designer, recorded with the reason the safety is no less than full compliance.
  • The design declaration also has a box for permitted exceptions under Regulation 411.3.3, where 30 mA protection of a socket-outlet is omitted on a documented risk assessment. The assessment must be attached.

"None" is a statement, not a blank

If there are no departures, write "None". A blank box leaves the reader unable to tell whether departures were considered.

04 · Certificate Guide

Section D: next inspection

Regulation 644.4 requires the recommended interval between initial verification and the first periodic inspection to be recorded. On the form the designer states the installation should be inspected and tested after an interval of not more than so many years or months.

The model notes say the interval should reflect the maintenance the installation is likely to receive. GN3 Table 3.2 gives the usual starting points: 10 years for a domestic installation, 5 years for commercial premises, 3 years for industrial, and shorter for places such as swimming pools and caravan parks.

05 · Certificate Guide

Sections E and F: signatories and supply

Section E gives the name, company and address for each signatory in Section C (up to two designers, the constructor and the inspector).

Section F records the supply: the earthing arrangement (TN-C, TN-S, TN-C-S PME, TN-C-S PNB, TT or IT), the number and type of live conductors, nominal voltage and frequency, prospective fault current Ipf, external earth fault loop impedance Ze, and the supply protective device. It also confirms supply polarity and flags any other sources of supply.

Which fault current to write

Ipf is the greater of the prospective short-circuit current and the prospective earth fault current, by enquiry or measurement. See prospective fault current explained.

In the app

Record test results hands-free on site

AI board scanner, voice test entry, and automatic BS 7671 validation — finish the certificate before you leave the property. From £6.99/mo.

Download on the App StoreGet it on Google Play

06 · Certificate Guide

Section G: particulars of the installation

  • Means of earthing: the distributor's facility or an installation earth electrode, with the electrode type, location and resistance where there is one.
  • Maximum demand, in kVA or amps.
  • Earthing conductor and main protective bonding conductors: material, cross-sectional area, and confirmation that connection and continuity were verified, with each bonded service ticked (water, gas, oil, structural steel, lightning protection, other).
  • Main switch: location, BS (EN), poles, current and voltage rating, and, where it is an RCD, its type, IΔn, time delay and measured operating time.

07 · Certificate Guide

Sections H, I and J: inspections, existing installation, schedules

Section H is the schedule of inspections, items 1.0 to 14.0, from the consumer's intake equipment through ADS, basic and additional protection, distribution equipment, circuits, isolation and switching, identification and notices, bath or shower locations, other special locations, and the prosumer's low voltage installation.

Section I is for comments on the existing installation when the work is an addition or alteration. Regulation 644.1.2 requires defects in the existing installation found during the work to be recorded, so far as reasonably practicable; defects that affect the safety of the new work must be put right before the certificate is issued.

Section J lists the attached schedules and continuation sheets. The schedule of test results carries the circuit-by-circuit readings: continuity, insulation resistance, polarity, Zs (check against maximum Zs values) and RCD operation.

08 · Certificate Guide

What the client is told

The model EIC includes guidance for the recipient. It tells them to keep the original safe and show it to anyone working on the installation, to press RCD test buttons six-monthly, to test AFDDs with a manual test button six-monthly, and to check SPD status indicators. Explain these at handover; they are the parts of the certificate a client actually acts on.

Frequently Asked Questions

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from electricians and apprentices

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-day free trial

Complete the EIC on site

Elec-Mate lays out the A4:2026 certificate section by section, with the schedules attached and the readings checked as you enter them.

Start your free trial

From £6.99/mo after the trial — no charge until day 8.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5
  • 7 days free, then from £6.99/mo
  • Cancel in one tap — no calls, no hassle
  • iOS, Android and web
  • Built to BS 7671:2018+A4:2026

Or download the app

Download on the App StoreGet it on Google Play
Certificate types
19Certificate types
Calculators
70+Calculators
Training courses
46+Training courses
AI specialists
8AI specialists