  1. 01What is a method statement?
    • AA written document describing how work will be carried out safely, step by step
    • BA record of the materials used on the project, and the cost of each of them
    • CA certificate confirming that a worker is competent, and trained, to carry out the task
    • DA document that lists only the hazards present in the work area, and nothing further

    Why: A method statement (also called safe system of work document) describes in detail how work will be done safely, including the sequence of operations and controls.

  2. 02What is the relationship between risk assessment and method statement?
    • AA method statement removes the need for a risk assessment of the activity that it covers
    • BThey are simply two names for the same one document, which is why they are issued together as RAMS
    • CThe method statement describes how to implement the controls identified in the risk assessment
    • DThe risk assessment is written afterwards to justify the method statement that was agreed

    Why: A method statement describes how to implement the control measures identified in the risk assessment, providing step-by-step safe working procedures.

  3. 03What information should a method statement contain?
    • AThe cost of the labour, plant and materials needed to complete the work
    • BA list of the legislation, and standards, that apply to the work being done
    • CDescription of work, sequence of operations, equipment, control measures, responsible persons
    • DOnly the start and finish dates of the project, and the agreed contract programme

    Why: Method statements should include work description, sequence of operations, equipment and materials, control measures, responsibilities, and emergency procedures.

Common questions

Is the Method Statements mock exam free?

Yes, it is free with no sign-up needed. Questions are pulled at random from a substantial bank, with a worked explanation on every question after you submit.

Can I retake the mock exam?

Yes. Every attempt picks a different random selection and reshuffles the options, so each retake gives you genuinely new questions. No limit on retakes.

Does this count as a qualification?

No. This is independent practice material and does not award a qualification, card or certificate. Where a subject has a formal qualification or card, you gain it through an approved provider.

Certificate types
19Certificate types
Calculators
70+Calculators
Training courses
46+Training courses
AI specialists
8AI specialists